Polar Night Energy and Lahti Energia are partnering on the Sand Battery project in Finland. Image: Polar Night Energy / Lahti Energia.

Technology provider Polar Night Energy and utility Lahti Energia have partnered for a large-scale project using Polar’s ‘Sand Battery’ technology for the latter’s district heating network in Vääksy, Finland.

- Advertisement -

The project will have a heating power of 2MW and a thermal energy storage (TES) capacity of 250MW, making it a 125-hour system and the largest sand-based TES project once complete.

It will supply heat to Lahti Energia’s Vääksy district heating network but is also large enough to participate in Fingrid’s reserve and grid balancing markets.

- Advertisement -

Polar Night Energy’s technology works by heating a sand or a similar solid material using electricity, retaining that heat and then discharging that for industrial or heating use.

This article requires Premium SubscriptionBasic (FREE) Subscription

- Advertisement -

Already a subscriber? Sign In

Try Premium for just $1

Full premium access for the first month at only $1
Converts to an annual rate after 30 days unless cancelled
Cancel anytime during the trial period

- Advertisement -

Premium Benefits

Expert industry analysis and interviews
Digital access to PV Tech Power journal
Exclusive event discounts

Or continue reading this article for free

- Advertisement -

The project will cut fossil-based emissions in the Vääksy district heating network by around 60% each year, by reducing natural gas use bu 80% and also decreasing wood chip consumption.

It follows Polar Night Energy completing and putting a 1MW/100MWh Sand Battery TES project into commercial operations this summer, for another utility Loviisan Lämpö. That project uses soapstone as its storage medium, a byproduct of ceramics production.

This latest project will use locally available natural sand, held in a container 14m high and 15m wide. Lahti Energia received a grant for the project from state body Business Finland.

Polar Night Energy will act as the main contractor for the construction project, with on-site work beginning in early 2026, and the Sand Battery will be completed in summer 2027.

“We want to offer our customers affordable district heating and make use of renewable energy in our heat production. The scale of this Sand Battery also enables us to participate in Fingrid’s reserve and grid balancing markets. As the share of weather-dependent energy grows in the grid, the Sand Battery will contribute to balancing electricity supply and demand”, says Jouni Haikarainen, CEO of Lahti Energia.

InterContinental London – The O2, London, UK

This isn’t just another summit – it’s our biggest and most exhilarating Summit yet! Picture this: immersive workshop spaces where ideas come to life, dedicated industry working groups igniting innovation, live podcasts sparking lively discussions, hard-hitting keynotes that will leave you inspired, and an abundance of networking opportunities that will take your connections to new heights!

Held alongside The Battery Show Europe, Energy Storage Summit provides a focused platform to understand the policies, revenue models and deployment conditions shaping Germany’s utility-scale storage boom. With contributions from TSOs, banks, developers and optimisers, the Summit explores regulation, merchant strategies, financing, grid tariffs and project delivery in a market forecast to integrate 24GW of storage by 2037.

Battery Asset Management Summit Europe is the annual meeting for owners, operators, investors, and optimisation specialists working with operational BESS assets across the continent. The Summit focuses on how to maximise performance and revenue, manage degradation, integrate advanced optimisation software, navigate evolving market and regulatory frameworks, and plan for repowering or end-of-life strategies. With insights from Europe’s most active storage markets, it equips attendees with practical guidance to run resilient, profitable battery portfolios as the sector scales.

Read Next

NHOA Energy has secured contracts from Engie for an 80MW/320MWh BESS at Engie’s Drogenbos power station, near Brussels, Belgium.

AFC and public-private-partnership (PPP) Cabeolica have inaugurated 13.5MW of wind power generation and 26MWh of battery storage in Cape Verde.

Cell manufacturing overcapacity and intense competition contributed to an 8% decline in the average cost of lithium-ion battery packs, according to BloombergNEF.

The UK’s National Energy System Operator (NESO) will offer grid connection offers up to 2035 to 283GW of projects following a reform of the process.

European energy independence is achievable if long-duration energy storage is factored into the mix, writes Oonagh O’Grady of Hydrostor.

Most Popular

Leave a Comment
Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected & This Is Prohibited!!!

We have detected that you are using extensions to block ads and you are also not using our official app. Your Account Have been Flagged and reported, pending de-activation & All your earning will be wiped out. Please turn off the software to continue

You cannot copy content of this app